Foundation Strengthening & Tilt Correction

Tilt Correction and Strengthening of a 27-Storey Residential Building, Guangdong

Foundation strengthening, underpinning and correction addressed differential settlement and overall tilt.

Client requirement

Foundation strengthening, underpinning and correction addressed differential settlement and overall tilt.

Engineering challenge

Analysis considered water-induced disintegration of soft rock, sloping bearing strata and pile-tip support, requiring coordination of new piles with the existing foundation.

Technical approach

New anchor-reaction jacked grouted steel pipe piles provided partial underpinning, with pilot holes, pile-tip grouting and pile-head sealing. Pile cutting enabled controlled-settlement correction, followed by restoration of the cut piles' load-bearing capacity.

Project value

The project connected underpinning, tilt correction and restored pile capacity under complex bearing-stratum conditions.

RELATED PROJECTS

Explore related work.

PROJECT QUESTIONS

Questions related to this work.

LET’S BUILD THE NEXT CHAPTER

Every building deserves thoughtful engineering.

Tell us about your project and explore the next step.

Discuss your project ↗