Client requirement
After topping out, persistent settlement and tilt affected lift installation, requiring stabilization and overall correction.
Technical approach
Ground information, settlement observations and calculations informed additional anchor-reaction jacked grouted steel pipe piles and pile-tip post-grouting before lifting the foundations and superstructure together.
Process control and project value
Multi-direction displacement and vertical-member stress monitoring, together with PLC synchronized lifting, controlled adjustment amounts and speeds during coordinated foundation strengthening and lifting.